Figure 214. Installing the front I/O expansion board
After you finish
1.  Reinstall the front I/O expansion board module. See “Install the front I/O expansion board module” on 
page 277.
2.  Reconnect the required cables.
3.  Reinstall the network adapter to the front I/O expansion board module. See “Install a network adapter” 
on page 180.
4.  Complete the parts replacement. See “Complete the parts replacement” on page 328.
Lenovo Neptune(TM) liquid-to-air (L2A) hybrid cooling module 
replacement (trained technician only)
Follow instructions in this section to remove and install the Lenovo Neptune
TM 
liquid-to-air (L2A) hybrid 
cooling module.
Important: This task must be operated by trained technicians.
Remove the Lenovo Neptune(TM) liquid-to-air (L2A) hybrid cooling module
Follow instructions in this section to remove the Lenovo Neptune
TM 
liquid-to-air (L2A) hybrid cooling module.
About this task
Important: Removing and installing this component requires trained technicians. Do not attempt to remove 
or install it without proper training.
Attention: 
•  Read “Installation Guidelines” on page 121 and “Safety inspection checklist” on page 122 to ensure that 
you work safely.
•  Power off the server and peripheral devices and disconnect the power cords and all external cables. See 
“Power off the server” on page 14.
Chapter 4. Hardware replacement procedures 281