3-14
Application Manual CDA3000
3 User interface and data structure
3.5 Commissioning Procedure for commissioning with the aid of the Application
Manual
1. Initial commissioning based on Operation Manual:
The precondition is initial commissioning with
the aid of the Operation Manual.
The user manual only covers adaptation of the
software functions.
If the settings from the initial commissioning based on the Opera-
tion Manual are not adequate for your application:
2. Selection of the optimum application data set
The application data sets record the typical
applications of the CDA3000 inverter module.
see table with overview of applica-
tion data sets (see section 4.2, Sel-
ection of application data set).
The application data set which best covers the
specific application is selected.
3. Custom adaptation of the application data set to the
application
The application data sets serve as the starting
point for application-oriented adaptation. Other
function adaptations are made to the parame-
ters in the function-oriented subject areas (see
Figure 3.2 in section 3.1 Data structure). Save
your settings by means of parameter 150 -
SAVE = START in subject area _15 FC-Initial
commissioning.
4. Checking the set application solution
To preserve the safety of personnel and
machinery, the application solution should only
be checked at low speed. Make sure the direc-
tion of rotation is correct. In case of emergency
the inverter power stage can be disabled, and
the drive stopped, by removing the ENPO
signal.