Operation
16K PLUS October 2019 5-11
Pre-Operation Checklist
Before operating Bale Runner check the following items:
Pre-Operation Check
Lug nuts Check that all lug nuts are present and torqued to the appropriate torque rating.
Pin retaining bolts Check for any missing or loose bolts or pins, replace or tighten as necessary.
Hydraulic hoses Inspect all hydraulic hoses and replace any worn hoses. Remember: Use a piece
of cardboard or wood to look for leaks, replace leaky hoses.
Hitch Jack Check that the hitch jack has been raised to its hightest postion and that the extension
leg has been fully retracted.
Warning Light Check that the Warning Light functions properly.
Hitch Safety Pin If traveling, check that the hitch safety pin is securely in place.
If gathering or stacking, check that the hitch safety pin has been removed.
Tire Pressure Check tire pressure to make sure it is within the specied range given in the “Machine
Specications” Section 2.
Hitch Connection Check the bolt system that connects the stacker to the tractor drawbar. A loose
connection will wear faster and possibly uncouple.
Breakaway Device Make sure the hitch safety chain is connected.
Lighting Make sure the lighting is hooked up and functioning properly.
Brakes Check to see that the brake system is hooked up and functioning properly if so
equipped.