11. Insert the Battery tray into the Battery Box.
Battery tray
Figure 2-34 Inserting the Battery Tray
12. Set the Batt Stopper bracket in place and secure with screw.
Screw
Batt Stopper
Figure 2-35 Secure Batt Stopper Bracket