Return the Server to the Normal Operating Position
Return the Server to the Normal Operating Position
Caution - Deploy any rack anti tilt mechanisms before installing the server into the rack.
Caution - The server weighs approximately 18.1 kg (40.0 lbs). Two people are required to carry
the chassis and install it into the rack.
1.
Push the slide rails into the slide rail assemblies in the rack as far as possible.
2.
Raise the server so that the rear ends of the mounting brackets are aligned with
the slide rail assemblies that are mounted in the rack.
3.
Insert the mounting brackets into the slide rails, and then push the server
into the rack until the mounting brackets encounter the slide rail stops,
approximately 30 cm (12 inches).
The server is now in the extended maintenance position.
Returning the Server to Operation 147

Table of Contents

Other manuals for Oracle SPARC S7-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle SPARC S7-2 and is the answer not in the manual?

Oracle SPARC S7-2 Specifications

General IconGeneral
BrandOracle
ModelSPARC S7-2
CategoryServer
LanguageEnglish

Related product manuals