6. Pull the mast cable out the inner mast and start to
lower it between the two masts until the next tape
marker is at the top of the cable carrier.
7. Use three of the cable clamps removed earlier to
secure the cable to the outer mast cable carrier.
Make sure the tape marker is at the top.
8. Raise the outer mast until the cable loop is visible
from the bottom of the mast.
9. Make sure the cable isn’t twisted, then put a
weighted roller into the cable loop.