Chapter 19 Initial Startup Procedure of Cube®
6) Inspect and Adjust Chemical and Water Delivery Systems
6c) Confirm Proper Function of Spot-Free Rinse System
PRESSURES AND FLOW RATES
TABLE 3
MODEL
PRODUCTION
GPD
PRODUCTION
GPM
REJECT
GPM
PUMP
PRESSURE
MEMBRANE GAUGE
PRESSURE
PSI 75% or better of
PUMP PRESSURE
PC 1000 WM
1000
0.7
0.9
180
No lower than 135
PC 2000 WM
2000
1.4
1.6
180
No lower than 135
PC 3000 WM
3000
2.1
2.3
180
No lower than 135
PC 4500 WM
4500
2.8
2.3
180
No lower than 125
PC 3000 STAND
3000
2.1
2.3
180
No lower than 135
PC 4500 STAND
4500
2.8
2.3
180
No lower than 125
PC 6000 STAND
6000
4.2
4.2 TOTAL
180
No lower than 130
EACH
PC 8000 STAND
8000
5.6
4.2 TOTAL
180
No lower than 130
EACH
PC 10,000 STAND
10,000
7
4.2 TOTAL
180
No lower than 130
EACH
PC 15,000 STAND
15,000
10.4
6.0 TOTAL
180
No lower than 130