5.4 Functional Test
5.4.1 Preparation
Once all components of the fire detection system are installed and wired:
1. Turn on the fire detection system.
2. Connect the laptop on which the FSP-5000-RPS programming software is installed to the
fire detection system.
3. Load the configuration.
Now perform the function tests (as described in 5.4.2 to 5.4.4 ).
5.4.2 Testing the Power Supply
1. Measure the voltage of the batteries.
The target values are12.0 V to 14.1 V, or 24 V to 28.2 V.
2. Test the power failure function
Remove the fuse and make sure that the failure of the power supply is indicated on the
display.
Make sure that the time limit for failure of the power supply is set to around 25 min (in
the configuration).
3. Restore the power supply.
Once the fire detection system is reconnected to the power supply, it automatically goes
into standby mode, and the power supply failure display disappears.
4. Test the battery failure function:
Remove the cables between the batteries and the BCM module.
Make sure that the time limit for failure of the batteries is set to around 25 min (in the
configuration).
Indication of battery failure can be delayed by up to 15 min.
5. Reconnect the cables between the batteries and the BCM module.
Once the connection with the batteries has been restored, the battery failure display
must be reset manually.
5.4.3 Testing the Conventional and LSN Functions
1. Testing a conventional/LSN loop:
Disconnect the conventional/LSN loop by detaching the cable connection to the
corresponding functional module.
Failure of the conventional/LSN loop must be indicated on the display.
Restore the connection between the conventional/LSN loop and the corresponding
functional module and reset the error message. Now test all automatic and manual
detectors.
2. Testing a conventional/LSN stub:
Disconnect the conventional/LSN stub by detaching the cable connection to the
corresponding functional module.
Failure of the conventional/LSN stub must be indicated on the display.
Restore the connection between the conventional/LSN stub and the corresponding
functional module and reset the error message. Now test all automatic and manual
detectors.
5.4.4 Testing the Addressing/Activation
1. Test the activation of the transmission devices (TD/DACT/TSN/GSM/X25/X31) by
triggering the corresponding assigned detector.