Loading/distributing material
- Use switch (1) to open the hopper.
Instruct the truck driver to dump the
material.
- Set the switches for the auger (2) and
the conveyor (3) to „auto“.
- Set the switches for the auger and the
conveyor on the remote controls (if ap-
plicable) to „auto“.
- Switch the conveyors on.
The limit switches for the conveyors
(4) must switch off when the material
has approximately reached the area
beneath the auger crossbeam.
- If necessary, carry out setting at the
eccentric shafts (5)
- Check that the material is conveyed
properly.
Manually switch on or off the conveyor
if the material is not conveyed properly
until a sufficient amount of material
lies in front of the screed.