7.2 Initial start-up
The initial startup of the Plant is carried by Ecolab service personnel.
If you have any questions, please contact your Ecolab F&B service partner
.
After assembly and once all connections have been established as described in the
chapter
Ä
Assembly and Installation , the system is ready for initial start-up.
Start up for the first time, as follows:
n Carry out the valve assignment.
Ä
Chapter 8.3.2.1 ‘Assign dosing station / valves’
on page 60
n Set general operating parameters.
Ä
Chapter 8.6 ‘Set the operating parameters’
on page 75
n Set up circuit parameters.
Ä
Chapter 8.7 ‘Set up the lubrication circuits’ on page 79
n Bleed the lubrication circuits and check the system for correct operation.
Ä
Chapter
7.2.4 ‘Bleed the lubrication circuits and check the system for correct operation’
on page 46
n When handing over the system to the customer, set up access passwords.
Ä
Chapter
8.3.5 ‘Issue PIN codes’ on page 68
Commissioning / operation