7.2.1 Performing valve assignment
Personnel:
n
Manufacturer
n
Service personnel
Protective equipment:
n
Protective eyewear
n
Protective gloves
n
Safety shoes
Material:
n
Electrical circuit diagram of the control unit
Requirements:
n The Lubo-DryExx
®
dosing station is fully installed.
n The controller is connected according to the operator's specifications.
n Operating media (compressed air
, track lubricant) are connected and available.
1. Switch the switch on the control cabinet to ‘1’.
ð
The system starts up, which takes approximately 1 min.
"DryExx Advanced-ETH"
ECOLAB Engineering
GmbH
releases via "Ethernet" selected,
valves assigned
Stat. ON/OFF
Archive
Parameter circ.
Param. Generaly
Logout
Message
LED-Test
Fig. 9: Home screen
ð
After a successful system startup, the ‘home screen
appears on the control
cabinet display
.
2.
On the Lubo-DryExx
®
metering station, set the air regulator for the control air of the
metering pump to approx. 3–3.5 bar
.
3.
Press the [ECOLAB
®
] logo.
time
setup
signals
language/Sprache
password
windows level
start up
Version Panel: V7.1
Version Hardware: V4.1
Return
ð
The ‘System settings’ screen appears.
4. [setup] Press .
setup:
selection
Return
setup dosing units/valves
setup communication
ð
‘setup: selection
appears.
5. Check the network settings.
Commissioning / operation