5. Move the stabiliser legs or extensions.
5a. Unscrew the red spool related with the stabiliser
leg or extension you want to move.
5b. Press the spool cursor with a sharp object for:
• Operate up/down the stabiliser leg.
• Retract the stabiliser extension/tilt the stabiliser
leg.
5c. Screw back the red spool as soon as the
movement is complete.
CAUTION
• Always contact an authorised service workshop after this operation, as they
must restore the correct crane operation.
• Release the knob and the spools to their initial position and protect them
with the control valve safety cover.
• The authorised service workshop must add the new security seal.
Ending crane operation
138 EFFER 265-315-395-525 Progress 2.0 CE