22. Power up the server .
23. If removed, install the front bezel .
ResultsResults
The installation is complete.
Installing the 4 LFF display port/USB optionInstalling the 4 LFF display port/USB option
PrerequisitesPrerequisites
Before you perform this procedure, make sure that you have a T-10 Torx screwdriver available.
ProcedureProcedure
1. If installed, remove the front bezel .
2. Power down the server.
3. If installed, open the cable management arm .
4. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5. Disconnect all peripheral cables from the server.
6. Remove the server from the rack .
7. Place the server on a flat, level work surface.
8. Remove the access panel .
9. Remove the middle cover .
10. Remove the front USB and DisplayPort blank.
Retain the screws. These screws will be used to secure the front USB and DisplayPort assembly.