Relative time setting Description
Last Period
The last period at this level. For example, if the current
date is 2007/05/30
- the Last Month category is 2007/04
- the Last Quarter category is 2007 Q1, assuming a
standard year of four quarters beginning in January
- the Last Year category is 2007
Same Period, Prior Higher-Level
Period
The same period in the most recent higher-level period.
For example, if the current date is 2007/05/30, which
falls in the second month of the second quarter of a
standard calendar year
- the Same Month, Prior Quarter category is 2007/02,
which is the second month of the first quarter
- the Same Month, Prior Year category is 2006/05,
which is the fifth month of the previous year
Period To-Date, Prior Period The periods-to-date in the context of the most recent
higher-level period. For example, if the current date is
2007/05/30, which falls in the second month of the
second quarter of a standard year.
the Quarter to Date, Prior Quarter category is a
specially constructed version of 2007 Q1 that contains
only the first and second months (January and
February) of that quarter
Custom A relative time period that you specify by changing the
predefined category details. For more information, see
“Example - Creating Custom Relative Time Periods.”
Cognos Transformer supports the following mechanisms for setting the current
period:
v automatic, based on the most recent date in the data source that updates the
current period
v manual, as set on the Time tab of the time dimension property sheet, or on the
diagram
v using the command line, by setting the -t option
For more information, see “-t option” on page 232.
v using an MDL script
For more information, see the Cognos Transformer Developer Guide.
Example - Creating Custom Relative Time Periods
This example illustrates how to create a set of custom relative time periods to meet
the specific reporting needs of your users.
Procedure
1. Suppose your first period is for the month 2007/03, which is two months
before the month in which the current period occurs. You specify the following
details:
v Current Period = 2007/05/30
Appendix D. Reference 329

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM Cognos and is the answer not in the manual?

IBM Cognos Specifications

General IconGeneral
DeveloperIBM
Data Sourceflat files
Operating SystemMicrosoft Windows
LicenseCommercial
Input SourcesSQL databases, Excel, CSV
PlatformMicrosoft Windows