©1999 Navia Aviation AS 21833-3.4 Maintenance Procedures
OPERATING MANUALNORMARC 7013
INSTRUMENT LANDING SYSTEM
C-15
6. Record the results of step (5) on FAA Form 6750-22. If the results are not within tolerance,
take appropriate action.
7. To determine if site effects are compromising the measurement, repeat steps (1) through
(5) at alternate distances.
8. Restore the facility to service.
5-23 thru 5-39 RESERVED.
5.40 LINE ENTRY OF NORMAL READINGS.
a. Object.
This procedure provides a method to complete a line entry of the normal parameters on FAA
Form 6750-26, with the equipment in normal configuration.
b. Discussion.
A line entry of the glide slope normal parameters is required after equipment transfer, before a
normal end-fire glide slope ground check, and periodically as required in chapter 4. This
check is made without adjustment to the equipment and can be performed from a remote
maintenance monitor (RMM). Computer generated data reports may be used in lieu of FAA
forms.
c. Test Equipment Required.
1. A portable ILS receiver (PIR).
meters300perscentimeter30=
5.1
cm45