1 Putting into Operation
This section describes the basic steps to be taken when setting up the R&S NRP2 for
the first time.
It contains the following topics:
●
unpacking
●
AC supply connection
●
switching the meter on and off
●
function testing and installing the meter
●
preset or default settings
●
front and rear views
1.1 Notes on putting into operation
Risk of instrument damage
Note that the general safety instructions also contain information on operating conditions
that will prevent damage to the instrument. The instrument's data sheet may contain
additional operating conditions.
Risk of instrument damage
Before putting the R&S NRP2 into operation, make sure that:
●
the sensor inputs are not overloaded
●
the meter’s outputs are not overloaded or wrongly connected
●
the ventilation holes are not obstructed
The meter may be damaged if these precautions are not observed.
Notes on putting into operation