Commissioning networked 'Stations'
9
43 | 17
Building Technologies
9 C- Commissioning networked 'Stations'
You will find information on converting a
'Station' in chapter 'Converting a standalone station to a networked station
[➙ 78]'.
Prerequisites
● The ↑ detector lines and C-NET devices are installed.
● The acceptance test has been carried out for the detector lines.
● The ↑ 'Station' is installed, but the batteries are not connected yet.
● The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
● Cerberus-Engineering-Tool is installed on the PC.
● The current firmware and ↑ BDV are available on the PC.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. Create a ↑ 'Site' and the 'Stations' in Cerberus-Engineering-Tool and pre-
configure, if required.
2. Prepare each 'Station' individually for commissioning - without BDV installation.
Link [➙ 75]
3. Connect the PC to each 'Station' individually. Link [➙ 27]
4. Initialize each 'Station' individually. Link [➙ 28]
5. Read-in the C-NET devices for all 'Stations'. Link [➙ 82]
6. Load the configuration from the 'Station' to the PC. Link [➙ 32]
7. Adapt the configuration in Cerberus-Engineering-Tool. Link [➙ 77]
8. Load the configuration from the PC to the 'Station'. Link [➙ 30]
9. Test the function of the 'Site'. Link [➙ 86]
10. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [➙ 30]
11. Disconnect the PC from the 'Station'. Link [➙ 27]
12. Perform the completion tasks. Link [➙ 86]