Commissioning networked 'Stations'
9
43 | 17
8
Building Technologies
A6V10210416_j_en_
--
Fire Safety
2018
-
-
29
9 C- Commissioning networked 'Stations'
You will find information on converting a
standalone '
Station
' to a networked
'Station' in chapter 'Converting a standalone station to a networked station
[ 78]'.
Prerequisites
The detector lines and C-NET devices are installed.
The acceptance test has been carried out for the detector lines.
The 'Station' is installed, but the batteries are not connected yet.
The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
Cerberus-Engineering-Tool is installed on the PC.
The current firmware and BDV are available on the PC.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. Create a 'Site' and the 'Stations' in Cerberus-Engineering-Tool and pre-
configure, if required.
2. Prepare each 'Station' individually for commissioning - without BDV installation.
Link [ 75]
3. Connect the PC to each 'Station' individually. Link [ 27]
4. Initialize each 'Station' individually. Link [ 28]
5. Read-in the C-NET devices for all 'Stations'. Link [ 82]
6. Load the configuration from the 'Station' to the PC. Link [ 32]
7. Adapt the configuration in Cerberus-Engineering-Tool. Link [ 77]
8. Load the configuration from the PC to the 'Station'. Link [ 30]
9. Test the function of the 'Site'. Link [ 86]
10. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [ 30]
11. Disconnect the PC from the 'Station'. Link [ 27]
12. Perform the completion tasks. Link [ 86]