Detailed commissioning steps
Rectify localization errors
15
86 | 178
15.20 Rectify localization errors
1. Use 'Topology' > 'Hardware tree' > ↑ 'Station' > ↑ Line card > Detector line to
select the corresponding ↑ detector line in the main menu.
2. Press the 'More Options' ↑ softkey and select 'Execute commands'.
3. Select the 'Accept replaced devices' command.
a The fault messages are no longer displayed.
If devices are missing or the device types do not corresp
topology, error messages will continue to be displayed.
15.21 Checking 'Site' function
Test the function of the ↑ 'Site' in the various test modes.
You will find information on testing a 'Site' in the 'Testing' chapter of document
A6V10211076. See chapter 'Applicable documents'.
See also
2 Applicable documents [➙ 11]
15.22 Carrying out final commissioning work
Checking the date and time
1. Check the date and time.
2. Adjust the date and time, if required.
– To do this, select 'Settings/administration' > 'System commands' > 'Set
system time' in the main menu.
Setting the PIN for access levels
1. Set the PIN for access levels 1, 2.1, 2.2, and 3.
– To do this, select 'Settings/administration' > 'Manage PINs' in the main
menu.
2. Fit the housing cover.
3. Label the installation plate, which should be outside on the housing, with the
site number and the date of commissioning.
– To do this, use a solvent-resistant pen.