137 © STULZ GmbH – all rights reserved EN/01.2019/G22
ec tower technical manual
Installing the front door
16. Fit the right-hand cover panel.
17. Fit the left-hand cover panel.
18. Fit the lower front panel.
19. Install the front door on the EC Tower.
20. Switch on the circuit-breaker (F20) by turning it to setting 1.
21. Close the door of junction box 1 using the supplied triangular socket wrench.
Setting the C7000AT controller
22. Switch on the unit via the master switch.
23. 
24. 
25. Check that outside air is not being sucked into the EC Tower.
26. 
Filling out the start-up report
27. 