Appendix A ________________________________________________________ Options Installation 
VAISALA ______________________________________________________________________ 283 
 
  0401-068 
Figure 152  Positioning Drilling Holes 
2. Drill three 20 mm holes with a depth of 70 mm using the drilling 
template. Make sure that the holes are drilled perfectly 
perpendicular. 
3.  Remove the template and clean the holes. 
4.  Insert the dowels into the holes and hammer them down until their 
edges are on the foundation level. Recommended dowels: HILTI 
HKD-S M16 x 65. 
5a.  Use the HILTI tool HSD-G M16 x 65 respectively a 14 mm  
mandrel bar and hammer the expanding mechanism of the wedge 
bolts down until the bolts are completely fixed inside the holes. 
5b.   Fasten the frangible mounting rods/foundation screws to the 
inserted dowels by hand. 
6.  Check the right orientation of the foundation screws. The breaking 
area (area with smaller diameter → contraction area) just above the 
welded nut on the frangible mounting rods/foundation screws must 
point upwards. 
7.  Place a washer between the foundation surface and the welded nut 
(see Figure 153 on page 284).