Verify that as the carriers are released Lane 2 Gate G5,
the large disk diverter D3 is activated and the carriers are
routed back to main track.
As the carriers enter the main track, verify the Main track
carrier detector (SICK Sensor) activates main track anti-
collision gate.
As a carrier is released by Gate G5, stop the carrier while
it is at the top section of the large disk and hold the carrier
still. Verify that diverter D3 remains activated.
Release the carrier. As the carrier completes its movement
around the disk and is detected by the Main track carrier
detector (SICK Sensor) and enters the main track, the
diverter is closed.
Continue APS track exercise until all carriers have been
cycled through the IM at least once.
At the i2000SR IM Pneumatic Panel, reverse the tubing
connections for Diverter DO EV2. This will restore normal diverter
operation.
Complete installation of i2000SR LAS
Using the ARCHITECT Service documentation, perform the
following:
• Installation of the i2000SR LAS Covers
i2000SR LAS Verification procedure
SCC Installation Verification procedure
The Accelerator APS i2000SR IM is complete.
Return to the Accelerator APS workcell installation procedure.
Refer to the Abbott Accelerator APS Acceptance Testing
section in Appendix C of the Accelerator APS Service Manual.
Ensure that all i2000SR IM checks have been verified.