4. Ensure that the breather system at the gear unit is properly
installed.
5. Ensure that the breather at the intermediate chamber is
properly installed and the quench fluid can drain off freely in
the event of a seal leakage, or, when medium must not be
released into the atmosphere, that a suitable drain system is
installed.
6. Check whether the delivered quench fluid (see enclosed
data sheet) is suitable or whether an alternative fluid must be
used in order to observe environmental protection regula-
tions, or for biological or other reasons. This must be compat-
ible with the medium, and must not adversely affect the O-
rings of the mechanical seals. Consult Börger GmbH
regarding this, if necessary.
7. Check the fill level in the intermediate chamber. On
standing versions, the quench fluid must reach halfway up
the shaft. Otherwise, the quench fluid (cf. data sheet) must be
refilled. If there is much more fluid in the intermediate
chamber than the optimum fill level when the mechanical seal
is intact, some of the fluid should be drained off in order to
prevent premature overflowing. Otherwise, the functionality of
the leak monitor may be compromised. In this regard, also
see
Ä
Chapter 6.2.2 “Lubricant fill level and changing the
lubricants” on page 123.
8. Ensure that the supply lines to the drive are connected and
secured according to the relevant regulations.
9. Provide a dry run protection such as a level monitoring
system in the substrate being fed, if required.
10. Ensure that the unit is properly grounded.
11. Check that the pipe connectors are attached correctly and
do not leak (torque for the connection between Börger
machine and pipe connector according to
Ä
Chapter 4.4.1
“Preparation for installation” on page 73).
12. Check that all screws and nuts, which may have become
loose during transportation and installation, are tight.
13. Ensure that the thick matter can fall out freely.
14. Make sure that the liquid phase can drain without being
hindered, and that the permissible pipe length has not been
exceeded.
15. Rectify all errors determined by this check.
Transportation, Storage and Installation
BA-RC40_EN, 17.01.2024www.boerger.de / www.boerger.com90