Re-install the cover by aligning the lower slot in the cover with the lower boss on the meter
body. Push the top of the cover into place and begin threading the two upper screws in place
then secure wrench tight for now. (G)
G
2) Push in at top
3) Start upper screws
1) Align at bottom
4) Lower screws last
13
Install the two remaining screws in the lower holes and secure wrench tight for now.
14
Inspect the perimeter on the back side of the cover to make sure the O-ring is seated properly.
If there is any “blue” protruding out between the cover and the meter body, remove the cover,
discard the O-ring and start over.
15
Tighten the cover screws to 12 N-m (8.9 Ft-lb) torque.
16
Remove the shop rag from the top of meter.
17
Install a new dome O-ring. Apply a light amount of petroleum jelly over the O-ring before re-
installing the cover.
18
Re-install the (8) 5 mm hex socket head screws to secure the meter dome to the meter. (B)
Tighten the screws in a crisscross manner until the wrench is tight, then torque to 10 N-m
(7.4 Ft-lb).
19
Re-install the WIP.
20
Reset the shear valves and power up.
21
Place dispenser in stand-alone mode and purge the meter.