Loading...
Retaining plate
Proportional valve
Retaining pin
Conduit
Coil
Ring Magnets
on conduits should
be up against
vapor barrier
NA version
shown
Figure 6.10: Proportional valve assembly
6.9 Meter Replacement - Removing Meter from Base
The procedure below is for removing the iMeter from the base casting. If the meter is to the far
right when viewing from side A, it may be helpful, but not necessary, to remove side column
covers as explained in the Product Tube Replacement section of this manual.
Refer to Fig 6.11 and Fig 6.12 on the following pages when performing these steps. Figures
6.13 and 6.14 are for loosening the rail screws. This is required only if removing the meter with
the base and coupling attached.
1
Trip the emergency shear valve.
2
Run a sale to drain line and relieve pressure.
3
Power down the dispenser and submersible pump at the circuit breakers inside the building.
4
Place a container under the filter funnel spout to catch fuel. (Remotes).
5
Remove filter and strainer to drain fuel. (Remotes).
6
Cut and remove the seal wires on the pulser and meter IEC. For NA iMeter, also remove seal
pins/slats and bracket.
7
Loosen (2) 5 mm Allen screws that secure the pulser to the meter. Remove pulser and set
aside on top of adjacent meter. (In most cases it is not necessary to disconnect the pulser
cable.)
8
Place container under the valve to catch fuel.
9
Remove product tube lock pin from valve and remove tube from valve.
10
Loosen (2) 10 mm hex screws that secure the valve retaining plate to the meter and rotate
retaining plate upward.
11
Pull valve out from meter and rotate valve and conduit out and away from meter.
WM048523 Rev 08 01/2019 89
6 Replacement Procedures

Table of Contents

Related product manuals