Chapter A8: Quality Assurance Process and Maintenance
Definium AMX 700 X-Ray System 5161515-1EN Rev. 6 (10 February 2008) A8-7
Operator Manual © 2008 General Electric Company. All rights reserved.
Figure A8-11 Quality Assurance Program screen
3. Press [QAP].
The Vertical Bar Calibration screen appears.
4. Press the [START] button to begin the Vertical Bar Calibration test.
NOTE: QAP requires that the system be in an idle state (without exposures) for at least 10 minutes before
the Vertical Bar Calibration portion of the test can begin. If the system has not been idle, a
countdown timer appears on the bottom of the screen and Vertical Bar Calibration will begin
automatically when the specified time has been reached.
Figure A8-12 Vertical Bar Calibration screen
5. Wait for the test to complete.
The Detector Check Tests screen appears.