GE H
EALTHCARE
D
IRECTION
GA091568, R
EVISION
5 VIVID E9 S
ERVICE
M
ANUAL
8 - 214 Section 8-9 - Casters and Brakes replacement
8-9-3 Pedal Mechanism replacement
8-9-3-1 Preparations
When preparing for the replacement, you must perform the following steps:
1.) Power down the VIVID E9
2.) Disconnect the Mains Power Cable from the wall outlet.
3.) Disconnect all probes and external I/O cabling.
4.) Remove both Side Covers.
5.) Remove the Foot Rest Bumper.
6.) Remove the Top Cover
7.) Remove the Front Cover
Figure 8-214 Pedal Mechanism Assembly
WARNINGWARNING
ENERGY CONTROL AND POWER LOCKOUT FOR VIVID E9.
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO
VOLTAGE GREATER THAN 30 VOLTS:
1. FOLLOW LOCK OUT/TAG OUT PROCEDURES.
2. TURN OFF THE BREAKER.
3. UNPLUG THE VIVID E9.
4. MAINTAIN CONTROL OF THE POWER PLUG.
5. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE, AS THERE ARE NO TEST POINTS TO
VERIFY ISOLATION. THE AMBER LIGHT ON THE OP PANEL ON/OFF BUTTON WILL TURN OFF.
BEWARE THAT THE MAIN POWER SUPPLY AND BACK END PROCESSOR MAY BE ENERGIZED EVEN IF THE POWER
IS TURNED OFF WHEN THE CORD IS STILL PLUGGED INTO THE AC OUTLET.
Signed
Date
TA G
&
LOCKOUT