4. Cut the cables to suitable length. Strip the cables and conductors.
5. Twist the cable screens into bundles and connect the bundles to the PE busbar
in the cubicle.
6. Connect any separate ground conductors/cables to the PE busbar in the cubicle.
Refer to section Use of fasteners in cable lug connections (page 61).
7. Connect the phase conductors to the output terminals. Use the tightening torques
specified in section Tightening torques (page 163).
8. Install the shrouding that was removed earlier and close the cubicle doors.
9. At the motor, connect the cables according to instructions from the motor
manufacturer. Pay special attention to the phase order. For minimum
radio-frequency interference, ground the cable shield 360° at the cable entry of
the motor terminal box, or ground the cable by twisting the shield so that the
flattened shield is wider than 1/5 of its length.
60 Electrical installation