Installation checklist
65
3ADW000194R0611 DCS800 Hardware Manual f us
Installation checklist
Checklist
Check the mechanical and electrical installation of the drive before start-up. Go
through the checklist below together with another person. Read the Safety
instructions on the first pages of this manual before you work on the unit.
Check
MECHANICAL INSTALLATION
The ambient operating conditions are allowed. (See Mechanical installation, current ratings
Ambient conditions.)
The unit is fixed properly on a vertical non-flammable wall. (See Mechanical installation.)
The cooling air will flow freely.
The motor and the driven equipment are ready for start. (See Planning the electrical
installation)
All screen terminals are checked for tightness.
All cable connections are seated properly.
ELECTRICAL INSTALLATION (See Planning the electrical installation, Electrical installation.)
The drive is grounded properly.
The mains (input power) voltage matches the drive nominal input voltage.
The mains (input power) connections at U1, V1 and W1 and their tightening torques are OK.
Appropriate mains (input power) fuses and disconnector are installed.
The motor connections at C1, D1 and F+, F- and their tightening torques are OK.
Proper function of E_Stop circuit and relay..
Fan power wiring connected.
The external control connections inside the drive are OK.
There are no tools, foreign objects or dust from drilling inside the drive.
Drive, motor connection box and other covers are in place.