The support bracket with the meter removed is shown in Fig 16.37.
Figure 16.37: Support bracket
13
Install new meter and secure using the two screws.
14
Reinstall tubes secure all connections.
15
Reinstall WIP magnet box onto meter and reinstall WIP.
16
Open all valves.
17
Turn on power.
18
Verify there are no leaks.
19
Check operation.