3. Piping connection
Keep the permissible length of every piping limitation to prevent a defect or cooling/heating failure.
CAUTION
Piping material:
Use the designated size (diameter and thickness) of refrigerant pipes.
Those pipes purchased locally may contain dust inside. Use dry nitrogen to blow out any dust.
Do not use standard pipe tees for branches, these can cause uneven refrigerant flow to the
indoor units. Optionally available standard branch kits should be used instead.
T-tube Separation tube Reducer
Prohibited OK
When replacing the unit, never use piping which has been used for previous installations. On-
ly use the new piping.
Piping preparation and installation:
Make sure that no dust or water enters the pipe during preparation or installation.
When installing the pipe, make bends as few as possible, and make radius as large as possi-
ble.
Cut the branch kit at the right size or use the reducer to match the pipe to the branch kit.
Piping treatment:
The pipes vibrate, expand, and contract during operation, so if loads are concentrated in one
area, it could cause cracks in the pipes. Provide the pipe supports every 2 to 3 m.
Make sure to insulate the refrigeration pipes separately with appropriately sized insulation as
described earlier. Make sure to overlap the ends to prevent any gap.
Brazing:
While brazing the pipes, be sure to blow dry nitrogen gas through them.
0.02 MPa
Pressure hose
Belows valve
Nitrogen gas
Rubber stopper
(continued)
- (06-33) - 3. Piping connection