A server of another model needs to be replaced with the RH8100 V3.
Impact on the System
This operation has no adverse impact on the system.
Prerequisites
Conditions
A cabinet is properly installed.
The installation environment is ready. For details, see 3.1 Installation
Overview.
Data
No data preparation is required for this operation.
Tools
The following tools are available:
ESD gloves
ESD wrist strap
Phillips screwdriver
Procedure
Step 1 Specify the server installation position.
Figure 3-2 shows the position in which the
oating nuts are installed.
When you install the guide rails, make sure that screws are not installed in
the four lower square holes shown in the Figure 3-2. The holes are used for
installing the chassis.
RH8100 V3 Server
User Guide 3 Installing the RH8100 V3