Crane operation
11.1 Before operating the crane
Operating Manual GMK6300L 3 112 xxx en 11 - 3
xx.xx.xxxx
9. Check
– RCL,
– lifting limit switch,
– seat contact switch and dead man's switch,
– emergency stop switch,
for correct operation. Have faulty units repaired;
à p. 11 - 9.
10. Check the position of the hoist ropes;
à p. 11 - 6.
11. Remove the keys from the key-operated
Override switches;
à p. 11 - 40.
12. Compare current rigging mode to display on RCL – enter current
rigging mode if necessary;
à p. 11 - 23.
13. Compare current reeving of hoist used against the display on the RCL –
enter current reeving if necessary;
à p. 11 - 29.
14. Check telescoping;
à Checks before starting work, p. 11 - 73.
15. Perform lamp test on the RCL;
à p. 11 - 20.
s

Table of Contents

Other manuals for Manitowoc Grove GMK6300L

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK6300L and is the answer not in the manual?

Manitowoc Grove GMK6300L Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK6300L
CategoryConstruction Equipment
LanguageEnglish

Related product manuals