Installation and commissioning
4.2 Mounting and connecting up a TIM
TIM DNP3
70 System Manual, 06/2014, C79000-G8976-C253-03
8. Turn on the power supply.
The TIM starts up. The LEDs indicate the current start-up activities (see separate section
Start-up activities
).
9. Once it has started up, the TIM can be supplied with its parameters (SDBs) using the
SINAUT diagnostics and service tool.
With the TIM 3V-IE DNP3 and the TIM 4R-IE DNP3, the SDBs can also be loaded on the
memory card of the S7-300 CPU, with the TIM 4R-IE DNP3, you can also use the
optional C-PLUG of this module for storage. The TIM receives then its configuration data
from the CPU during startup or takes it from the inserted C-PLUG.
4.2.6
Installing a TIM 4R-IE DNP3 as a standalone device
Order of installation
To install the TIM 4R-IE DNP3 as a standalone device on an S7-300 rail, follow the steps
below in the order shown:
1. Place the TIM on the standard rail and push it in towards the bottom.
2. Screw the TIM securely into position.
3. Connect the TIM to the power supply. Since this is a separate TIM rack, this does not
need to be the power supply of the CPU with which the TIM is connected via Ethernet.
4. If you are connecting the TIM to an external modem, the insert the 9-pin D-sub connector
of the modem connecting cable into the X1 or X2 connector of the TIM 4R-IE DNP3 and
screw it tight.
5. Connect the TIM to the S7-CPU(s) or the PC of the control center. With a
TIM 4R-IE DNP3, this is via Ethernet.
6. Once the wiring is completed, the power supply can be turned on.
The TIMs start up. The LEDs on each TIM indicate the current start-up activities, refer to
the section Commissioning the TIM (Page 72).
7. Once it has started up, the TIM can be supplied with its parameters (SDBs) using the
SINAUT diagnostics and service tool.
With the TIM 3V-IE DNP3 and the TIM 4R-IE DNP3, the SDBs can also be loaded on the
memory card of the S7-300 CPU, with the TIM 4R-IE DNP3, you can also use the
optional C-PLUG of this module for storage. The TIM receives then its configuration data
from the CPU during startup or takes it from the inserted C-PLUG.