D301271 1013 - FGEN - multi protocol
12-3
Application example
12.1.3 New project in the Simatic Manager
1 Create a new project in the Simatic Manager using the "File New"-command
2 Add a Simatic station to the project using the "Insert station..."-command. In this example a
"Simatic 300 station" is used.
The configuration of the PROFINET-network is then done in the software's hardware configuration
12.1.4 Setting the PG/PC-interface
In order to be able to build up communication between the PLC and your PG/PC via Ethernet, the
respective interface/ network card of the PG/PC has to be activated.
The configuration of the interface is done via the "Set PG/PC Interface" command.
Open this dialog in the Simatic software for example via the "Options Set PG/PC Interface..."
command or directly in the Windows Control Panel for your PG/PC.
Figure 12-1:
Selecting a
Simatic station
Figure 12-2:
Command "Set
PG/PC Inter-
face..."

Table of Contents