Close MCB without Synchronization (Dead Bus Operation MCB)
Automatic operation
the "AUTOMATIC" operating mode has been selected
the release "Dead bus operation MCB" is set to "ON"while inconfiguration mode
no voltage is applied to the busbar
the mains voltage is applied (in the case of emergency power the mains settling time has
been finished)
the mains voltage and frequency are within the preset limits
the "response: GCB is open" is present (the GCB is open)
the input "release MCB" is set
With a load sharing via CAN-Bus (Woodward units)
- none of the MCBs may be closed if a isolated operation in parallel with other gensets
is possible
- the unit with the lowest unit number will be the first to close its MCB
Manual operation
the "MANUAL" operating mode has been selected
no voltage is applied to the busbar or busbar voltage is below 20V
the mains voltage is applied
the "response: GCB is open" is present (the GCB is open)
the input "release MCB" is set
the button "MCB ON" has been activated
with a load sharing via CAN-Bus (Woodward units)
- none of the MCBs may be closed in case of a isolated operation in parallel with other
gensets
- the unit with the lowest unit number will be the first to close its MCB
Opening the GCB
The generator power circuit breaker is opened both when the relay "Command: Close GCB" de-energizes (only if
"constant" has been selected for the GCB closing relay in configuration mode), and via the closure of the relay
"Command: Open GCB". The GCB will be opened under the following circumstances:
In case of a response of a mains monitor with decoupling to GCB
while in operating mode "STOP"
if alarm class 2 or 3 occurs
when actuating the button "GCB OFF" or "MCB ON" (depending on the preset switch
logic) while in manual operation or load test operation
when actuating the button "STOP" while in manual operation
when settling automatically while in the AUTOMATIC operating mode
after synchronizing the MCB
prior to switching to the dead busbar of the MCB in a automatic transfer switching
while in sprinkler operation, provided that no emergency power case is present
Opening the MCB
The mains power circuit breaker is opened via the closure of the relay "Command: Open MCB" (the "constant"
setting is not possible for the MCB). The MCB will be opened under the following circumstances:
In case of a respond of a mains monitor, provided that the mains decoupling is set to
MCB
In the case that the emergency power (loss of mains) is responding and successful engine
start
following synchronizing of the GCB
prior to the closing of the GCB in an automatic transfer switching
when actuating the button "MCB OFF" or "GCB ON" (depending on the preset switch
logic) while in manual operation or load test operation

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Woodward GCP-20 Series and is the answer not in the manual?

Woodward GCP-20 Series Specifications

General IconGeneral
BrandWoodward
ModelGCP-20 Series
CategoryControl Unit
LanguageEnglish

Related product manuals