5702269-C Safety and Product Compliance Guidelines 1-7
Pinnacle™ Plus+ 10 kW
• For delta-connected mains, primary and supplemental Protective Earth (ground)
wires must be connected.
• Install and operate this device in an overvoltage category II installation only.
• Use only a shielded power cable on the output power connector.
• CE marked power supplies: install and operate this device only in a pollution
degree 2 or better environment, which means an indoor location such as a
computer room, office, or factory floor where only non-conductive pollution
occurs during operation. Occasionally, condensation causes temporary
conductivity when the device is not operating.
• Non-standard connectors for input and/or output power must be inaccessible to
the operator.
• Advanced Energy Industries, Inc., may provide a supplementary protection circuit
breaker in the power supply. You must provide a branch circuit backup fuse with
a UL LISTED Type K5 or RK5 fuse or equivalent that is rated 15 A minimum and
no more than four times full-load amps (not to exceed 125 A for 50 A or less rated
breaker, and not to exceed 175 A for 51 through 100 A rated breaker).
Note: See “Electrical Specifications” on page 3-4 for more information about the
electrical specifications of your power supply.
• If your unit does not have a circuit breaker, install and operate it with an AE-
approved circuit breaker on the AC input to provide the required over-current
protection. In addition, you must provide the primary circuit protection (such as
the branch circuit backup fuse).