Cisco ONS 15454 - DLP-G599 Turn on and Verify AC Office Power on the ONS 15454 M2 Shelf

Cisco ONS 15454
516 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Step 3 Attach the DC ETSI power cables to the DSUB power connectors of the DC power module (see the following
figure).
Step 4 Tighten the screws to a torque value of 4 in-lb (0.45 N-m) to secure the cable.
Figure 167: Connecting Office PowerDC Power Module (ETSI Only)
Use only pressure terminal connectors, such as ring and fork types, when terminating the battery,
battery return, and frame ground conductors.
Note
Before you make any crimp connections, coat all bare conductors (battery, battery return, and frame
ground) with an appropriate antioxidant compound. Bring all unplated connectors, braided strap,
and bus bars to a bright finish, then coat with an antioxidant before you connect them. You do not
need to prepare tinned, solder-plated, or silver-plated connectors and other plated connection surfaces,
but always keep them clean and free of contaminants.
Caution
When terminating power, return, and frame ground, do not use soldering lug, screwless (push-in)
connectors, quick-connect, or other friction-fit connectors.
Caution
Step 5 Return to your originating procedure (NTP).
DLP-G599 Turn On and Verify AC Office Power on the ONS 15454 M2 Shelf
This task measures the power to verify correct power and returns for the ONS
15454 M2 shelf.
Purpose
VoltmeterTools/Equipment
Cisco ONS 15454 Hardware Installation Guide
251
Installing the ONS 15454 M2 Shelf
DLP-G599 Turn On and Verify AC Office Power on the ONS 15454 M2 Shelf