CompletedDescription
NTP-G13 Install the Rear Cover (ANSI Only), on page 118
NTP-G14 Install DWDM Equipment, on page 123
NTP-G15 Install the Common Control Cards, on page 131
NTP-G301 Connect the ONS 15454 Multishelf Node and Subtending Shelves to an MS-ISC-100T
Card, on page 138 or NTP-G295 Connect the ONS 15454 Multishelf Node and Subtending
Shelves to a Catalyst 2950 or Catalyst 3560, on page 146
NTP-G298 Configure a Cisco Catalyst 2950 or Catalyst 3560 (Active and Standby) for a ONS
15454 Multishelf Node, on page 152 (if you completed NTP-G295 Connect the ONS 15454
Multishelf Node and Subtending Shelves to a Catalyst 2950 or Catalyst 3560, on page 146)
Step 3 Complete the DLP-G35 Inspect the Shelf Installation and Connections , on page 145.
Step 4 Complete the DLP-G36 Measure Voltage , on page 146.
Step 5 Continue with “ Connect the PC and Log into the GUI ” document.
Stop. You have completed this procedure.
DLP-G35 Inspect the Shelf Installation and Connections
Use this task to inspect the shelf installation and connections and verify that
everything is installed and connected properly.
Purpose
NoneTools/Equipment
NonePrerequisite
Procedures
RequiredRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Procedure
Step 1 Make sure all external wiring connections on the backplane (that is, power, ground, alarms, etc.) are secure.
If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it.
Step 2 (ETSI only) To check that the FMEC cover is seated correctly, verify that it can be easily closed without
disturbing cables.
Step 3 Return to your originating procedure (NTP).
Cisco ONS 15454 Hardware Installation Guide
145
Installing the ONS 15454 M12 (ANSI and ETSI) Shelf
DLP-G35 Inspect the Shelf Installation and Connections