CompletedDescription
DLP-G604 Install the TNC, TNCE, TSC, or TSCE Card, on page 262
NTP-G269 Install the Standard Door of the ONS 15454 M2 Shelf, on page 216
Step 2 Complete the DLP-G601 Inspect the ONS 15454 M2 Shelf Installation and Connections , on page 268.
Step 3 Complete the DLP-G602 Measure DC Voltage on the ONS 15454 M2 Shelf, on page 268.
Step 4 Continue with Connect the PC and Log into the GUI
Stop. You have completed this procedure.
DLP-G601 Inspect the ONS 15454 M2 Shelf Installation and Connections
Use this task to inspect the shelf installation and connections and verify that
everything is installed and connected properly.
Purpose
NoneTools/Equipment
NonePrerequisite
Procedures
RequiredRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Procedure
Step 1 Make sure all external wiring connections (that is, power, ground, alarms, and so on) are secure. If a wire or
cable is loose, return to the appropriate procedure in this chapter to correct it.
Step 2 Return to your originating procedure (NTP).
DLP-G602 Measure DC Voltage on the ONS 15454 M2 Shelf
Use this task to measure the power to verify correct power and returns.Purpose
VoltmeterTools/Equipment
Before installing the DC power, check the voltagePrerequisite Procedures
RequiredRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Cisco ONS 15454 Hardware Installation Guide
268
Installing the ONS 15454 M2 Shelf
DLP-G601 Inspect the ONS 15454 M2 Shelf Installation and Connections

Table of Contents

Other manuals for Cisco ONS 15454

Related product manuals