5 Connection PKE-SWD for motor-protective circuit-breaker PKE12/32/65
5.5 Commissioning
SmartWire-DT module IP20 01/20 MN05006001Z-EN www.eaton.com 127
At the PKE trip block, set the corresponding values for the overload trip or
the time delay setting to overcome current peaks.
Connect the SmartWire-DT external device plug with the adapted Smart-
Wire-DT connecting cable.
5.5 Commissioning
The automatic addressing of all modules in the SmartWire-DT network is per-
formed via the gateway (actuation of the configuration pushbutton on the
gateway) during commissioning. During the addressing process the Smart-
Wire-DT diagnostics LED flashes. Once the addressing process is com-
pleted, the LED indicates a green continuous light.
1
2
1
2
SWD4-8SF2-5
+ 15V
SWD4-8SF2-5
+ 15V
SWD4-8SF2-5
SWD4-100LF8-24
SWD4-3LF8-24-2S
SWD4-5LF8-24-2S
SWD4-10LF8-24-2S

Table of Contents