Loading...
You have determined the position on the RH8100 V3 for installing an
indicator board interface module.
Tools
ESD gloves
Packaging materials, for example, an ESD bag
M3 Phillips screwdriver
Hardware
Spare indicator board interface module
Procedure
Step 1 Wear an ESD wrist strap or ESD gloves. For details, see 1 Safety Instructions.
Step 2 Connect all cables to the indicator board interface module. See step (1) in Figure
5-33.
Step 3 Close the upper cover for the indicator board interface module. See step (2) in
Figure 5-33.
Figure 5-33 Installing an indicator board interface module
Step 4 Insert the indicator board interface module into the slot. See step (1) in Figure
5-34.
Step 5 Close the latch to secure the indicator board interface module. See step (2) in
Figure 5-34.
RH8100 V3 Server
User Guide 5 Removing and Installing Parts of the RH8100 V3
Issue 30 (2019-12-19) Copyright © Huawei Technologies Co., Ltd. 148