Operation 6-1
6 Operation
6.1 Overview
At this point, we have installed the S-920, connected it to the necessary facilities, performed the sub-
system checks, calibrated and adjusted the options, and are ready to begin final configuration for program
generation. The sections that follow describe the general sequence of actions necessary to write and run a
new dispensing program. References to FmXP are included as a guide. For detailed information on
FmXP, please consult the Fluidmove User Guide. It is assumed the system has been powered up and
FmXP is running. This section covers the following topics:
• Installing the Dispensing Valve • Creating a New Program
• Adjusting the Air Pressure • Installing Fluid on the Dispensing Valve
• Establishing Machine Offsets • Starting a Production Run
• Positioning the Conveyor and Dispensing Head • System Shutdown
• Camera Operation
" NOTE Refer to Section 5 - Calibration and Adjustment for the following procedures:
• Focusing the Camera • Z-head Counterbalance Force Adjustment
• Calibrating the Camera • Adjusting the Height Sensor Probe
• Adjusting the Service Station Height
WARNING! CAUTION!
DO NOT operate the Spectrum Series S-920 Dispensing System unless you
have been trained to do so. Operating the dispensing system without proper
training may result in personal injury or dispensing system damage.
6.2 Safety First
Operation of your S-920 Dispensing System involves heat, air pressure, electrical power, heat,
mechanical devices, and the use of hazardous materials. It is essential that every person servicing or
operating the dispensing system fully understands all hazards, risks, and safety precautions. Refer to
Section 2 - Safety for important safety information.
6.3 Startup
Refer to Section 4 - Power Up and Testing for details on system and Fluidmove startup/shutdown
procedures.