Groundsmaster 4100--D/4110--D Hydraulic SystemPage 4 -- 79
NOTE: The front frame needs to be lowered from the
main frame to allow clearance to remove the hydraulic
reservoir from the machine.
Removal (Fig. 55)
1. Park machine on a level surface,lowercuttingdeck,
stop engine, engage parking brake and remove key
from the ignition switch.
2. Remove front cutting deck (see Cutting Deck Re-
moval in the Service and Repairs section of Chapter 8
-- Cutting Deck).
3. Read the General Precautions for Removing and
Installing Hydraulic System Components at the begin-
ning of the Service and Repairs section of this chapter.
4. Drain r eservoir into a suitable c ontainer.
5. Disconnect hydraulic hoses from reservoir. Label
disconnected hydraulic lines for proper installation.
6. Remove straps (items 4 and8)thatsecure reservoir
tofrontframe.Removefeltstraps(item5)frombetween
straps and reservoir.
7. To allow front frame to be lowered for reservoir re-
moval, remove hydraulic tubes that connect hydraulic
components on front frame ( wheel motors and front
deck PTO manifold) to components on main frame. Put
caps or plugs on open hydraulic lines and fittings.
8. Chockr earwheelstopreventthemachinefrommov-
ing. Use jack or hoist to raise front of machine and sup-
port machine with jackstands.
9. Support front frame to prevent it from moving.
10.Removecapscrews(item31),flatwashers(item28)
andflangenuts(item30)thatsecurefrontframetomain
frame.
11.Carefully lower front frame assembly to allow clear-
anceforreservoir removal.Once lowered,supportfront
frame to prevent it from shifting.
12.Carefully remove hydraulic reservoir from machine.
Inspection
1. Clean hydraulic reservoir and tank strainer with sol-
vent.
2. Inspect reservoir for leaks, cracks or other damage.
Installation (Fig. 55)
1. Using a wrench, turn tank strainer into port from
1--1/2 to 2 full turns beyond finger tight.
2. Position reservoir to machine.
3. Carefully raise front frame assembly to main frame.
Align frame mounting holes and support front frame to
prevent it from moving.
4. Secure front frame to main frame with cap screws
(item 31), flat washers (item 28) and flange nuts (item
30). Tighten two (2) fasteners at rear of frame before
tightening top four (4) fasteners.
5. Lower machine to ground.
6. Position felt straps (item 5) between straps and res-
ervoir.Securer eservoir tofrontframewithstraps(items
4 and 8).
7. Remove caps and plugs from hydraulic lines and fit-
tings that were placed during the removal process. Us-
ing labels placed during reservoir removal, connect
hydraulichoses andtubesto fittings onreservoir,wheel
motorsandhydraulicmanifold(seeHydraulicHoseand
Tube Installation in the General Information section of
this chapter).
8. Install front cutting deck (see Cutting Deck Installa-
tion in the Service and Repairs section of Chapter 8 --
Cutting Deck).
9. Fill reservoir with new hydraulic fluid to proper level.
10.Properly fill hydraulic system (see Charge Hydraulic
System in this section).
11.Stopengineandcheckfor hydraulicoilleaks.Check
hydraulic reservoir oil level.
Hydraulic
System