Storage
BMTW-SVN01F-EN 13
Storage
Tracer Summit BCU panels are designed for indoor installation only. If
you must store the panel at the job site before installation, make sure it is
stored indoors in a controlled environment. Acceptable storage tempera-
tures range from –50°F to 150°F (–46°C to 66°C), with a relative humidity
from 10% to 90%, noncondensing.
CAUTION
Avoid Equipment Damage!
Store the BCU cover and logic board off site until most or all building
construction is complete. Failure to do so could damage the BCU cover
and logic board.
Hardware Installation Checklist
This checklist summarizes the steps required to properly install Tracer
Summit system hardware. See specific chapters for detailed guidelines
and procedures.
Panel Placement (Chapter 2))
• Install the BCU in a controlled indoor environment, away from elec-
trical interference and vibration.
• Mount the BCU securely.
• Observe the recommended clearances.
Power Supply Wiring (Chapter 3)
• Be sure all electrical wiring complies with applicable codes.
• Connect the power supply wiring to the BCU.
• Check the power supply wiring for shorts.
• Inspect the BCU printed circuit card for any visible signs of damage.
• Check for proper LED operation.
• Install all warning labels.
Assignable Input Wiring (Chapter 3)
• Inspect all terminations at TB1 for binary and analog (universal)
inputs.
• Inspect the universal input jumper wiring for proper configuration.
UCM Wiring (Chapters 4 and 5)
• Inspect all UCM communication wiring between devices.
• Make sure all connections are shielded properly.
• Set/inspect the DIP switch settings for each UCM.