Appendix D – Application examples
493
Example – Synchronisation through drive-to-drive link
In this example, there are two drives, the first of which is position-controlled and
uses absolute positioning in linear mode. The second drive is synchronised with the
first one via the drive-to-drive link.
Five references are given to the first drive: 75 mm, 75 mm, 125 mm, 125 mm and
-400 mm. The second drive will move to the same positions at the same speed.
FPBA-01
FEN-11
0 75 150 275 400 mm
M
FPBA-01
FEN-11
M
EnDat
EnDat
1 2 3 4
5
Master
Follower

Table of Contents