Operation principle and hardware description 49
P958 Harmonics factory
tests
The full-power current harmonics, power factor (PF) and DC injection tests are
done.
The grid voltage and frequency are set to the nominal values in these tests.
While the inverter operates at the nominal active power, current harmonics and
voltage harmonics are measured with a power analyzer. The power factor is
tested and measured with different power levels from 10% to 100%.
P959 Efficiency factory
tests
The efficiency test is done at the ambient room temperature with internal
auxiliary power. The inverter is operated at different power levels and it is
measured with a power analyzer. The euro efficiency is calculated according to
EN 50530.
P960 Custom factory
tests
In addition to the tests done for P945, P957, P958 and P959, power limiting
tests, controllable Power Factor (PF), inverter DC power operation, loss of DC
power, loss of auxiliary power, flicker and anti-islanding with RLC load tests are
done.
Printed documentation
R700 English With options R707, R708 and R711, the supplied printed manuals are in the
selected language and the rest of the documentation is in English. The
delivered documentation set may also include English manuals.
To request safety stickers in languages other than English or manuals in
French, Spanish and Russian to be supplied on a USB drive select the P902
Customized option.
R707 French
R708 Spanish
R711 Russian
Code Name Description

Table of Contents