Electrical installation 77
7
Electrical installation
This chapter describes the electrical installation of the inverter.
Insulation test
Inverter
The inverter is tested for insulation at the factory. Do not do voltage withstand or insulation
resistance tests on any part of the inverter.
AC output cables
Make sure that the insulation of the AC output cables obey the local regulations before you
connect them to the inverter.
PV generator
Make sure that the insulation of the PV generator obeys the local regulations and the
manufacturer instructions. The PV generator must be completely disconnected from the
inverter during the insulation test.