Service and troubleshooting
8.4 EST3 Installation and Service Manual
Removing or replacing circuit modules
When removing or replacing circuit modules, always remember
to:
1. First disconnect the battery then remove AC power.
Removing or replacing circuit modules when power is
applied will damage the equipment.
2. Avoid applying excessive force to the snap-rivet fasteners
that lock the plug-in modules in place. If needed, use the
extraction tool provided in the hardware kit.
Recommended spares list
As a general guideline, 10% of the quantity installed or a
minimum of 1 each of the following installed equipment should be
available as spare:
• Power supply
• Local rail modules
Amplifiers (if no backup installed in system)
• Printer ribbon
As a general guideline, 10% of the quantity installed or a
minimum of 3 each of the following installed equipment should be
available as spare:
• Monitor modules
• Control modules
• Heat detectors
Ionization smoke detectors
Photoelectric smoke detectors
• Base, detector
Duct detector filter kits
Breakglass replacement for pull stations
Breakglass replacement for warden stations
Horn, bell, strobe, and speaker
System batteries should be replaced at recommended intervals.
Stocking of spare batteries is not recommended because of
shelf-life limitations.