Installation
EST3 Installation and Service Manual
5.18
System installation sequence
Follow these general instructions when installing a panel as part
of an EST3 system. Refer to the installation sheets that came
with the product for specific instructions. The EST3 Installation
Sheets book contains copies of the installation sheets.
1. Install the equipment enclosure backbox at the required
location and pull all the required conductors through the
conduit into the backbox.
2. Verify the field wiring. Refer to Table 5-3.
3. Install the chassis assemblies that go into the panel.
4. Install the primary and booster power supplies.
5. Install all rail modules and control / display modules in their
required locations.
6. Apply power to the panel. Refer to the topic “Cabinet power-
up procedure” in Chapter 6.
7. Download an initial startup version of the CPU database, and
clear panel troubles. See the topic “Creating an initial startup
version of the project database,” later in this chapter.
8. Connect field wiring and clear any field wiring problems.
9. Download the final applications program. Refer to Chapter
6, “Power-up and testing.”
10. Disconnect the SDU from the panel.
11. Verify proper operation. Refer to the topic “Detector, input
module, and output module testing” in Chapter 6.
12. Fill out a Certificate of Completion for the system. Example
forms are included in Chapter 5.