Issue 08/2013 Page 60
MAPLA- Modular energy supply system for load lifting magnets
Installation and commissioning
General safety instructions
Danger
Danger to life through electric shock
y
All work on the iMAPLA system, visual inspections for
maintenance purposes or cleaning work during operation of
the system can lead to potentially fatal injury through electric
shock.
► Switch o the drive unit before all inspection or
maintenance work on the generator or switch box.
► Secure the drive unit before being switched on accidentally
(e.g.remove the ignition key and keep it in asafe place).
► During operation, never connect or disconnect plug
connections.
Danger
Danger to life!
y
Strong, permanent magnetic elds can impair the operation
of active implants/pacemakers.
► Persons with pacemakers are not allowed to remain in the
vicinity of lifting magnets when switched on.
► Always maintain asucient safety clearance from the lifting
magnet.
Warning
Risk of injury and risk of damage!
y
When working on the iMAPLA system, insuciently qualied
persons put themselves at risk and can damage the system.
► The assembly, connection and commissioning of the
iMAPLA system and work on the electrical systems may only
be carried out by authorised, qualied and specially trained
personnel.
► Carry out all connection work according to applicable
national regulations (in Germany: these include VDE
specications).